Proper operation of organic fertilizer production line using belt conveyor

2023/07/17

The belt conveyor function can not run normally for a long time, which is related to whether the application of organic fertilizer production line can be properly operated and whether it can be maintained. Therefore, before applying the belt belt conveyor, operate the machine according to the regulations.

(1) Before starting, carefully check the components of the organic fertilizer equipment, pay attention to whether there is other dirt on the belt, and it can run when there is no problem after inspection. When several belts are connected, the starting sequence is to run successively from the pouring end to the material end.

(2) After the start of the organic fertilizer production line, the first high speed of a circulation system, after checking the normal operation of each part, it can be operated with load. Belt belt conveyor belt sound card frame must be firmly connected, can not have cracks, deformation or abnormal sound.

(3) In the operation of organic fertilizer equipment, if the belt direction of the belt conveyor is found to run off, run off and other abnormal conditions, it should be adjusted immediately. When the belt runs off, do not put anything between the drum and the belt. The tightness of the belt is not suitable, and the tension device should be adjusted immediately.

(4) Often check the protective grounding and insulation layer of the equipment, the motor should often use the instrument panel to accurately measure and check, and maintain and maintain on time.

(5) Belt belt conveyor application should often remove the soil on the belt roller bucket. Do not use a triangle scraper, shovel, or wooden stick to clear the machine without turning off the machine.

(6) In organic fertilizer equipment, the feeding on the belt must be symmetrical, to avoid too much feeding, smashing the belt, endangering the stable operation of mechanical equipment.

(7) Before shutting down the organic fertilizer production line, the feeding should be terminated first, and after all the raw materials on the belt are unloaded, it can be shut down.

(8) Check the position of the belt belt conveyor after stopping, and do a good job in the cleaning work.